Construction progress on March 27, 2013.

New Theatre, Studio Arts Complex on Schedule for 2014 Opening

March 28, 2013 

Hamilton’s new theatre and studio arts building is on track to be finished in July, 2014. When complete the $46.8 million complex will encompass 81,000 square feet. View construction progress on the construction site’s webcam.

More ...
The new Theatre, Studio Arts complex under construction at Hamilton College on Feb. 11.

Theatre, Studio Arts Complex Taking Shape

February 14, 2013 

The new theatre and studio arts building under construction is taking on a distinctive shape with its steel foundation in place. When complete the $46.8 million complex will encompass 81,000 square feet. View progress on the construction site's webcam.

More ...
Tracy Adler, Susanna White, Katharine Kuharic, artist Julia Jacquette, Rebecca Murtaugh, Robert Knight and Hamilton students in Jacquette's studio.

Senior Art Concentrators, Faculty Make Annual Trek to NYC Studios

February 4, 2013 

After their original plans to visit the studios of professional artists fell through in October due to damage caused by Hurricane Sandy, nine senior art concentrators and art faculty were able to reschedule the always-anticipated trip and visit New York City on Jan. 24-27.

 

More ...
Construction site of the new theatre, studio arts complex.

Theatre, Studio Arts Complex Construction Under Way

December 20, 2012 

Hamilton’s latest major building project is well under way with the construction of the theatre and studio arts building progressing on schedule. Bill Huggins, associate director of Physical Plant, says the project is on track to be finished in July, 2014. When complete the $46.8 million complex will encompass 81,000 square feet.

More ...
Alexandra Nasto '13 with her acrylic painting "Untitled" (top).

Alexandra Nasto '13: From Museum Intern to Exhibitor

November 26, 2012 

Alexandra Nasto’s ’13 summer internship at the New Britain (Conn.) Museum of American Art (NBMAA) led to one of her works being exhibited at the museum’s Juried Members Show in October.  Nasto, a curatorial intern at the NBMAA from May to August 2012, submitted an acrylic painting she had completed as part of Hamilton Professor Bill Salzillo’s design class last spring. The painting was one of the works selected by juror Robert Burns, director of the Mattatuck Museum in Waterbury, Conn.

More ...

Theatre, Studio Arts Facilities Get Green Light

Charles A. Gaetano Construction Corp. of Utica is Construction Manager

June 4, 2012 

Having approved design construction documents for a new theatre and studio arts building, the Board of Trustees on June 2 authorized the officers of the college to enter into a contract with Charles A. Gaetano Construction Corp. of Utica to build new studio arts and theatre facilities in an amount not to exceed $46.8 million. Construction will begin this month and completion of the building is expected in summer 2014.

More ...